Danube Bridge Rehabilitation
Project Description
This project involves the replacement of the bridge superstructure with a single span, prestressed, composite, concrete box beams with semi-integral abutments. Additional work includes minor substructure modifications/repairs, as well as related roadway adjustments and restoration.
Project Update
The bridge is now open, but due to weather conditions, some final tasks will be completed in the spring.
Project Location
Danube Court between Hackney Drive and Olsen Drive.
Bid Date: April 11, 2024
Contractor
Eagle Bridge