West Dorothy Lane Resurfacing

Project Description

The scope of this project along Dorothy Lane includes milling and applying a 2.5-inch asphalt resurfacing over approximately 3.14 miles. The project extends from the intersection with South Dixie Highway to Haig Avenue, just west of the intersection with Wilmington Pike.

Project Update

The Engineering Department will open bids in February 2025 to select the contractor for the project. Construction is anticipated to begin in the summer of 2025. Please check back for updates in the spring of 2025.

Project Location

The western terminus of the project is at the corporation limit with the City of Moraine and extends east, stopping just short of Wilmington Pike.

Dorothy Project Map

Bid Information

Bid Date: February 6, 2025

Bid Results          Bid Tab

Contractor: To be determined

Contact Information

Project Engineer: Chad Ingle
Email: chad.ingle@ketteringoh.org
Phone: 937-296-2436