West Dorothy Lane Resurfacing
Project Description
The scope of this project along Dorothy Lane includes milling and applying a 2.5-inch asphalt resurfacing over approximately 3.14 miles. The project extends from the intersection with South Dixie Highway to Haig Avenue, just west of the intersection with Wilmington Pike.
Project Update
Concrete curb spot repairs along Dorothy Lane will commence in April, reducing traffic to one lane in the affected areas. This phase is expected to last through May. Milling of existing asphalt and new pavement replacement will begin in summer, during which traffic will be limited to one lane in each direction, and delays are expected.
Project Location
The western terminus of the project is at the corporation limit with the City of Moraine and extends east, stopping just short of Wilmington Pike.
Bid Information
Bid Date: February 6, 2025
Contractor: John R Jurgenson
Contact Information
Project Engineer: Chad Ingle